Biogas project in a Philippine pig farm
- Nov 09, 2018 -

The project signed a contract on November 2, 2017. The biogas fermentation tank has a volume of about 2,000 square meters (effective volume of about 1900 square meters), and is equipped with a 200KW generator set and a biogas purification device. Shipment on January 4, 2018, and construction of civil works began in early November 2017. Fermentation tank installation, pipeline and electrical installation, generator installation and feeding operation began on March 22, 2018.  And all equipment, civil works and preliminary commissioning of the entire project have been basically completed By June 22, 2018. 